New look website

Whilst there has been a slight delay to work starting on site, with the contractor now due on site on Monday 28th May, this hasn’t held up the launching of the updated Whitby Esk Energy website.  The new website will enable us to keep everyone up-to-date with the construction phase and with generation once the turbine is commissioned.

Update on project – April 2012

Whilst there is nothing showing on site yet plenty has been going on in the background.

Many thanks to Mike Ford who is liaising with the contractor Bentley’s, as project manager, on behalf of Esk Energy (Yorkshire) Limited. The relationship with Bentley’s is going well and they are keeping us informed at every stage.

With any project the unexpected crops up. Currently we are looking at the power connection with the national grid. This may lead to costs that had not been anticipated due to changes in rules on work undertaken near railway lines. Fortunately we have a contingency built into our budget but there may be delays to the planned schedule.