Latest Tweets

  • Whitby Esk Energy - Ruswarp Hydro turbine commissioned 12/12/12. Now exporting electricity to the grid!
  • We can now generate electricity!
  • Share issue closes today - last chance to buy shares before generation starts.
  • Turbine turned for the first time yesterday! Watch it in action http://t.co/WrUmSDvD
  • Close to commissioning the turbine now. If there are no more glitches, commissioning and testing should be completed by the 31st October.

Monthly Archives: June 2012

Upgrading the fish pass

Preparing site

Preparing site

Work is well underway on upgrading the fish pass.  Weather permitting, it is due for completion the first week in July.

 

Looking up the fish pass

Looking up the fish pass

Looking down the fish pass

Looking down the fish pass

Co-op North Yorkshire Area Committee Visit Site

The Co-op North Yorkshire Area Committee visited the site on Wednesday 13th June to find out more about the project.   Fortunately the rain held off and from the river bank opposite they were able to see the work that has started on upgrading the fish pass.   We have received a lot of support from the Co-op nationally with setting up the company and marketing the share issue.  Therefore, we were pleased to have the opportunity to discuss with the local committee members the difference the support has made to the running of the project.

Co-op area committee visit site

Co-op area committee visit site